In 1973 when marble hill was first proposed public service indiana psi now duke energy said the construction cost would be a whopping 700 million the largest capital project in indiana history.
Marble hill nuclear power station.
This is one of the more unique abandoned properties in indiana not only for its previous life s purpose but for the way it remains today.
Marble hill nuclear power station was an unfinished nuclear power plant in saluda township jefferson county near hanover indiana usa.
Some of the surrounding properties are still occupied so explorers beware.
In 1984 the public service company of indiana announced it was abandoning the half finished nuclear power plant on which 2 5 billion had already been spent.
Purdue university s reactor one was constructed in 1962 but its status as a private research reactor means it operates well below boiling conditions and is not a public power provider.
Marble hill nuclear power plant is a now demolished never completed power generating facility in marble hill indiana.
Tucked neatly away in the farmlands of nabb indiana lies the marble hill nuclear power plant.
Below are weather averages from 1971 to 2000 according to data gathered from the nearest official weather station.
All work stopped in 1984 after 2 7 billion had been expended.
In 1984 the public service company of indiana announced it was abandoning the half finished nuclear power plant on which 2 5 billion had already been spent.
Nuclear power plant unfinished unbuilt abandoned nuclear power plant.